Graybar - Tampa, Florida
Location: 4507 Oak Fair Boulevard | Tampa, FL 33610
Project Type: New Construction
Project Cost: $5.5 million
Size: 42,120 square feet
Owner: Graybar Electric Company, Inc.
Architect: Curran Architecture
Start Date: December 2017
Completed: December 2018
Scope:
Holladay Construction Group has completed construction on a new industrial building for Graybar’s Tampa, Florida headquarters. Site clearing for the new building began in December 2017, with sitework beginning in February 2018. The building was completed in December 2018 and features over 8,500 square feet of office space and a 33,500 square foot warehouse. In 2020, the project achieved LEED certification from the USGBC.